The litigation against the New Acland Coal Mine involved a major and lengthy hearing in the Land Court of Queensland, followed by judicial review and a subsequent appeal.
Background to the case
The New Acland Coal Mine is located amidst farmlands on the Darling Downs, 35 km north-west of Toowoomba in Queensland.
It is operated by New Acland Coal Pty Ltd (NAC), a wholly-owned subsidiary of the New Hope Group.
Stage 1 of the mine commenced operations in 2002. It expanded to Stage 2 in 2005 and by 2012 the mine produced 5.09 million tonnes of thermal coal per annum (Mtpa).
NAC applied in 2007 for Stage 3 of the mine to produce 9 Mtpa of coal from new pits to the south of the existing mine.
In Queensland, the major approvals required for large mines (or expansions of existing mines) under State and Federal legislation are:
- a mining lease under the Mineral Resources Act 1989 (Qld) (MRA);
- an environmental authority under the Environmental Protection Act 1994 (Qld) (EPA); and
- approval under the Environment Protection and Biodiversity Conservation Act 1999 (Cth) (EPBC Act).
Stage 3 of the New Acland Mine required two mining leases under the MRA for the additional area of land to be mined and an amendment to the existing environmental authority under the EPA. A map showing the land affected by the three stages of the mine is available here.
A range of other approvals may be required depending on the nature and location of a mine and its associated infrastructure, such as a water licence to extract groundwater or surface water under the Water Act 2000 (Qld).
The Queensland Coordinator-General declared Stage 3 of the mine a “significant project” in 2007 (the term for this designation later changed to being a “coordinated project”) under the State Development and Public Works Organisation Act 1971 (Qld) (State Development Act). This legislation provides an environmental impact statement (EIS) process for large projects but does not actually approve the projects occuring. An EIS under it is fed-back into other approval processes such as under the MRA and EPA.
The EIS process for the mine commenced in 2007 but stalled in 2012 when the then (Newman-LNP) Queensland Government announced it did not support the project due to the damage the mine would cause to prime agricultural land.
A revised, smaller Stage 3 project was proposed – reducing the proposed mine output to 7.5 Mtpa – and re-evaluated under the State Development Act. The Queensland Coordinator-General issued a report in December 2014 recommending the revised Stage 3 project be approved.
Concurrently with the Queensland assessment of the mine, it was assessed under the EPBC Act using a bilateral agreement and subsequently approved by the Commonwealth Environment Minister in early 2017.
The applications for the mining leases and amendment of its existing environmental authority for the mine under Queensland law were the subject of an objections hearing in the Land Court of Queensland.
Objections to the mine expansion
Over 30 objections were made by surrounding farmers and landholder groups to the revised Stage 3 proposal when it was publicly advertised for objections under the MRA and EPA in 2015.
The focus here is on the objection of a landholder group, the Oakey Coal Action Alliance (OCAA), which was one of 12 objectors who actively participated in the objections hearing in the Land Court.
OCAA objected to the mining lease and the amendment of the existing environmental authority for Stage 3 of the mine on numerous grounds, in summary including:
- groundwater depletion
- noise
- air quality
- economic benefits of the mine were overstated
- loss of agricultural land being contrary to intergenerational equity
- poor past performance of NAC and
- prejudice to the public interest.
A mammoth trial
The Land Court of Queensland hears objections to a mine under the MRA and EPA.
The objections to the revised Stage 3 expansion of the mine were referred to the Land Court in 2016 and Member PA Smith was assigned to the hearing. He was a very experienced judicial officer who had heard many cases against proposed mines in the past, including the proposed Alpha Coal Mine.
The large number of objectors and complex evidence in the case led to a mammoth trial, the longest in the 120 year history of the Land Court.
The hearing took almost 100 sitting days, during which almost 2,000 exhibits containing many tens of thousands of pages of material, and well in excess of 2,000 pages of submissions were received by the court. 28 expert and 38 lay witnesses gave evidence.
Member Smith ultimately recommended the applications for the mining leases and the amendment to the environmental authority be rejected in New Acland Coal Pty Ltd v Ashman & Ors and Chief Executive, Department of Environment and Heritage Protection (No. 4) [2017] QLC 24, delivered on 31 May 2017.
In summary, the major reasons for recommending the mine be rejected included because:
- the inadequacies of the groundwater modelling and, consequently, the unacceptable risks to groundwater for surrounding farmers
- the make-good agreements for landholders who may be affected were inadequate and practically impossible for landholders to enforce
- the impacts of the mine on land in the top 1.5% of agricultural land in Queensland meant that approval would not provide for intergenerational equity
- neighbouring landholders had experience unacceptable noise levels in the past and conditions requiring lower noise limits could not be imposed because to do so would be inconsistent with conditions imposed by the Coordinator-General.
Matthew Stevens, a senior business writer with the Australian Financial Review, described the judgment as “eye-opening and deeply concerning” and an “unqualified and brutally humiliating courtroom failure …” for the New Hope Group.
Judicial review overturns decision
On 15 June 2017 NAC filed an application for judicial review in the Supreme Court of Queensland seeking to have the Land Court’s decisions recommending rejection of the mining lease applications and refusal of the amendment of the environmental authority declared invalid, quashed and set aside based on 15 grounds, 3 of which were later abandoned. The remaining grounds were, in summary:
- ground 1 – the Land Court’s reasoning on noise & the Coordinator-General’s conditions;
- ground 2 – consideration of possible breaches of NAC’s current EA;
- ground 3 – inquiry into past performance of DEHP;
- ground 4 – consideration of the EPP (Noise) and the appropriate level of evening and night operations;
- ground 6 – consideration of the Xstrata case;
- ground 7 – whether intergenerational equity is a mandatory consideration;
- ground 9 – consideration of intergenerational equity under the MRA;
- ground 10 – groundwater is irrelevant to consider under the EPA and MRA;
- ground 12 – breach of natural justice;
- ground 13 – apprehended bias;
- ground 14 – unreasonableness & irrationality;
- ground 15 – sufficiency of reasons regarding groundwater.
Pending the outcome of the judicial review application, NAC applied for a stay of:
- the Land Court’s decisions;
- the pending decision of the Minister administering the MRA on whether to approve or refuse the mining leases; and
- the pending decision of the Chief Executive administering the EPA on whether to approve or refuse the amendment of the environmental authority.
NAC’s application for these stays was dismissed by Applegarth J on 23 June 2017.
Bowskill J heard the judicial review application on 19-23 March 2018 in the Supreme Court at Brisbane. Her Honour indicated on 2 May 2018 that she would allow the application on the basis of:
- ground 10, in relation to groundwater quantity not being within the jurisdiction of the Land Court to consider in an MRA and EPA objection hearing;
- ground 7, in relation to intergenerational equity, consequent upon the conclusion in relation to groundwater (ground 10); and
- ground 1(aii) in relation to noise and inconsistency with the Coordinator-General’s conditions.
Final orders were made on 28 May 2018, remitting the matter to the Land Court for rehearing before a different member but largely on the basis of the findings of fact made by Member Smith (excluding groundwater quantity issues).
Environmental authority refusal set aside
On 14 February 2018, the Department of Environment and Science (DES) made a final decision to refuse the environmental authority amendment application for the project. That decision was enveloped in the judicial review proceedings against the Land Court’s decision and was subsequently set aside when NAC succeeded in those proceedings.
Rehearing in Land Court
Following Bowskill J’s decision to set aside Member Smith’s decision, a new member of the Land Court (President Kingham) reheard the applications within the constraints imposed by Bowskill J on 2-4 October 2018.
On 7 November 2018, President Kingham delivered her decision on the rehearing and recommended (in essence) that:
- NAC must apply to the Coordinator-General to lower:
- the evening (6-10pm) noise limit from 42dB to 35dB;
- the night (10pm-7am) noise limit from 37dB to 35dB; and
- apply the new noise limits from the commencement of the environmental authority.
- Subject to the Coordinator-General and DES lowering the noise limits in the draft environmental authority, the environmental authority and mining leases be approved with amendments to the conditions reflecting the reasons of the Court (e.g. adding a new condition F9 that “The holder must make all noise monitoring data publicly available, online, and in real-time”).
- If the noise limits are not lowered, the applications be refused.
On 2 February 2019 the Coordinator-General granted NAC’s application to change the noise conditions as recommended by the Land Court.
Appeal pending
On 30 May 2018 OCAA appealed against Bowskill J’s decision to the Queensland Court of Appeal.
OCAA’s (10-page) outline of argument is available here.
The appeal is listed for hearing on 27 & 28 February 2019.
Key documents
Environmental authority for stage 2
- Environmental authority for stage 2 of the mine (Exhibit 15 in the Land Court), dated 14/7/2015.
Applications & EIS for stage 3
- Initial advice statement under the State Development Act for Stage 3, April 2007.
- EIS under the State Development Act for Stage 3, 2007-2014.
- Coordinator-General’s report recommending approval of mine, 2014.
- Draft environmental authority for stage 3 of the mine (Exhibit 9), dated 28/8/2015.
- Map of the mining leases for the mine around the town of Acland.
- Application and approval of mine under EPBC Act, 2007-2017.
OCCA objections to stage 3
- OCAA objection to the mining lease application, 30/6/2015.
- OCAA objection to the application to amend the environmental authority, 2/10/2015.
Expert reports on noise
- Noise joint expert report (JER) (Exh 406), 22/2/2016.
- Shane Elkin report on noise for NAC (Exh 114), 18/3/16.
- John Savery report on noise for OCAA (Exh 1886), 24/3/16.
- John Savery additional report on noise for OCAA (Exh 938), 1/6/16.
Expert reports on groundwater
- IESC 2014 advice, 10/4/14.
- IESC 2015 advice, 10/12/15.
- Groundwater JER (Exh 405), 16/2/16.
- Irvine & Durick statement of evidence (SoE) for NAC (Exh 418), 16/2/16.
- Currell SoE for OCAA (Exh 435), 24/2/16.
- Werner SoE for OCAA (Exh 436), 24/2/16.
- Durick affidavit for NAC (Exh 815), 11/4/16.
- Barnett SoE for NAC (Exh 826), 10/5/16.
- Currell supplementary SoE for OCAA (Exh 824), 6/5/16.
- Werner supplementary SoE for OCAA (Exh 833), 5/5/16.
- Supplementary groundwater JER (Exh 825), 11/5/16.
- Currell & Werner supplementary SoE for OCAA (Exh 1116), 2/6/16.
- Barnett supplementary SoE (Exh 1113), 27/6/16.
- IESC 2016 report (Exh 1915), 14/12/16.
- Barnett further SoE for NAC (Exh 1907), 20/2/17.
- Currell further SoE for OCAA (Exh 1918), 9/3/17.
- Werner further SoE for OCAA (Exh 1919), 10/3/17.
- Barnett SoE in reply for NAC (Exh 1911), 20/3/17.
OCAA closing submissions
- OCAA closing submissions, 13/9/2016
- OCAA submissions on Land Court process (requested by the Land Court), 30/9/2016.
First Land Court decision
- Decision of the Land Court recommending refusal of the EA and ML: New Acland Coal Pty Ltd v Ashman & Ors and Chief Executive, Department of Environment and Heritage Protection (No. 4) [2017] QLC 24, delivered on 31/5/2017.
OCAA application for costs
- OCAA submissions on costs, 16/6/17.
- Decision of the Land Court adjourning costs application until judicial review application decided: New Acland Coal Pty Ltd v Ashman & Ors (No. 5) [2017] QLC 58.
Judicial review application
- Application for judicial review, filed 15/6/2017.
- Application for stay, filed 15/6/2017.
- OCAA’s submissions resisting stay application, filed 23/6/2017.
- Decision dismissing the stay application: New Acland Coal Pty Ltd v Smith (Member of the Land Court of Queensland) [2017] QSC 216 (delivered ex tempore) Applegarth J, 23/6/17.
- Directions orders for hearing, made 17/7/2017.
- Amended application for judicial review, dated 28/11/2017.
- OCAA outline of argument, dated 23/11/2017.
- Decision of Bowskill J allowing the application in relation to grounds 10, 7 and 1(aii): New Acland Coal Pty Ltd v Smith & Ors [2018] QSC 88, delivered 2/5/18.
- Decision of Bowskill J on final orders & costs: New Acland Coal Pty Ltd v Smith & Ors (No 2)[2018] QSC 119, delivered 28/5/18.
Rehearing in Land Court
- OCAA’s outline of argument for rehearing, 18/8/18.
- OCAA’s submissions on “existing mining operations”, 3/10/18.
- OCAA bundle of maps for site visit (Exhibit E).
- Decision of President Kingham on rehearing: New Acland Coal Pty Ltd v Ashman & Ors (No 7) [2018] QLC 41, delivered 7/11/18.
Coordinator-General change of conditions
- NAC application to change the EA noise conditions, 3/12/18.
- Coordinator-General report changing the noise conditions, 12/2/19.
Appeal to the Court of Appeal
- Notice of Appeal, filed 30/5/18.
- OCAA outline of argument (25-page version), filed 11 July 2018. [The President of the Court of Appeal did not accept this outline as it exceeded 10 pages. His Honour ordered OCAA to file a 10-page version.]
- OCAA outline of argument (10-page version), filed 25 July 2018.
Thanks to OCCA, represented by the Environmental Defenders Office (Qld) Inc, for providing its documents for use in this case study.
Further information about the case is available on the EDO website.
-
Frank Ashman, President of the Oakey Coal Action Alliance, protesting against the New Acland Mine
Photo: Dan Peled AAP (2016)
- New Acland Coal Mine
-
New Acland Coal Mine amidst farmland
Photo: Lock the Gate
-
West Pit was 300 m from Glen Beutel’s house in Acland in September 2018 (viewed north)
Photograph by Dr Tanya Plant (2018)
-
West Pit was 300 m from Glen Beutel’s house in Acland in September 2018 (viewed south-southeast)
Photograph by Dr Tanya Plant (2018)
-
Extension of South Pit outside Stage 2 mine footprint in September 2018
Photograph by Dr Tanya Plant (2018)
Media reports about this case
Acland coal mine: Queensland Land Court recommends scrapping expansion, ABC News, 30 May 2017.
Court recommends $900m New Acland mine be rejected, The Guardian, 31 May 2017.
Court rejects New Acland mine expansion, Sydney Morning Herald, 31 May 2017.
Lawyers win major battle in Qld coal war, Lawyers Weekly, 31 May 2017.
Land court decision rocks New Acland Mine, Chinchilla News, 31 May 2017.
Landholders celebrate New Acland decision, Queensland Country Life, 1 June 2017.
How New Hope earned its Acland smack-down, Financial Review, 1 June 2017.
Oakey left shocked at Land Court ruling on Acland mine, Courier Mail, 2 June 2017.
New Hope says it’s not giving up on controversial $900m expansion of Acland coal mine, Courier Mail, 16 June 2017.
New Hope accused judge of ‘bias’, Queensland Times, 23 June 2017.
New Acland court hearing fast tracked, The Toowoomba Chronicle, 17 July 2017.
Let Acland coalmine expand or jobs will go, says New Hope, The Australian, 19 July 2017.
Revelations from the New Acland coal mine case, Reneweconomy, 25 July 2017.
Acland coal mine expansion uncertainty leaves jobs in limbo, ABC News, 6 August 2017.
New Acland’s difficult balancing act ahead of decision, Toowoomba Chronicle, 31 January 2018.
New Acland Coal mine expansion given second chance by Queensland Government, ABC News, 13 February 2018.
Queensland accepts court block on New Acland coalmine expansion, The Guardian, 14 February 2018.
Qld govt blocks Acland coal mine expansion, The Australian, 14 February 2018.
Queensland government blocks coal mine expansion, The Age, 14 February 2018.
Environmentalists, farmers claim partial win on New Acland, Toowoomba Chronicle, 14 February 2018.
New Acland coal mine expansion back on the table after Land Court decision rejected, ABC News, 2 May 2018.
Court revives New Acland mine expansion, Sydney Morning Herald, 2 May 2018.
New Hope buoyed by court ruling on New Acland’s $900m coal mine expansion, Australian Financial Review, 2 May 2018.
New Hope spent $1.2m promoting New Acland mine before Queensland election, The Guardian, 9 May 2018.
Alleged Acland mine expansion investigated, SBS News, 31 May 2018.
Mining company accused of expanding Acland coalmine without permission, The Guardian, 31 May 2018.
New complaints investigated at $900m Darling Downs mine, Brisbane Times, 1 June 2018.
Queensland Land Court gives New Acland expansion New Hope, Australian Mining, 8 November 2018.








